Golden Square Update #8

Reading Time: < 1 minute

It’s certainly going to be a busy week for the construction workers at the Golden Square development site with paving, pipe works and building work to start.

Balfour Beatty Construction will be continuing with paving and step unit installations. Paving grouting will also start this week to ensure a smooth and attractive finish to the Golden Square paths.

Pipe works are underway with duct installations and gully connections alongside building DPC brickwork and bolt set grouting installations.

A Scheme Sign will be installed outside of the development site this week.

Local businesses surrounding the Golden Square development site are still open, so make sure you show them your support.

For more information about the Golden Square click here.

Don’t forget to follow us on Twitter at @JQDTbirmingham for the latest updates on the Jewellery Quarter.

To download this update in PDF format, click here.

Share this