Golden Square Update #13

Reading Time: < 1 minute

Excavation works and paving on the plaza section of the Golden Square development site kick starts a busy week for Balfour Beatty construction workers.

Drainage works continue outside of the Big Peg alongside the installation of ACO drainage challenges. Glass seam, step and retail units will also resume fitting this week.

Duct and Duct box installations continue as well as the 2nd fix electrical and 2nd fix carpentry, which start this week.

The site’s usual working hours of Monday – Friday 7.30am – 5.30pm will be increased this week as works on the plaza continue on Saturday 20th September to lower an existing drain.

For more information about the Golden Square, click here.

Don’t forget to follow @JQDTBirmingham on Twitter for all of the latest updates from the Jewellery Quarter.