Golden Square Update #9

Reading Time: < 1 minute

Balfour Beatty construction workers at the Golden Square development site are working hard in the summer heat in another busy week in the Jewellery Quarter.

Excavation works on Vyse Street will continue, together with paving and kerbing works. Pipe works are also underway with drainage channels and duct installations continuing this week.

Step units are being prepared, as metal thread bases and streetlight bases are installed. Paving on the promenade has now started, with grouting to ensure a smooth surface.

Bricks, blocks and timber roof joists are also going up this week. The Balfour Beatty construction team is becoming increasingly busy as it approaches the near completion of the Golden Square.

For more information about the Golden Square click here.

Don’t forget to follow us on Twitter at @JQDTbirmingham for the latest updates on the Jewellery Quarter.

To download this update in PDF format click here.

 

Share this